IraqIQ-05Renewable energy

Solar and wind at 8.5% of power generation by 2030

Where does the pledge stand?

Progress seen ConfidencePossible

We therefore see progress, Satellite imagery shows the project's panels built on its site between December 2024 and October 2026, though imagery cannot show the operating capacity.

20% of the time between the NDC and the deadline has passed.

Last updated: 18 November 2026What do the status and confidence mean?

What did the country pledge?

solar PV and wind as part of Iraq’s electricity mix (8.5% of generation mix by 2030)
From the English translation · Page: PDF 17 (printed 10)
Target
8.5% of generation
Deadline
2030
Baseline before the pledge
According to Ember, renewables’ share of Iraq’s power generation fell from 4.36% in 2019 to 1.62% in 2024, mostly hydropower that declined with drought, while solar stayed at 0.29%. Sources
Condition
The document does not say whether it is conditional
What we measure
The share of solar and wind in electricity generation in Ember’s yearly data.

How do we know?

  1. 1Ember yearly electricity generation dataDataset · 2026
  2. 2Shafaq News: Shams Basra solar project begins operations with 250 MWOpen-source media · 11 May 2026
  3. 3Sentinel-2 imagery of the Shams Basra project site, December 2024 and October 2026Satellite imagery · 16 October 2026
The full assessment

Baseline before the pledge: According to Ember, renewables’ share of Iraq’s power generation fell from 4.36% in 2019 to 1.62% in 2024, mostly hydropower that declined with drought, while solar stayed at 0.29%.

The target is 8.5% by 2030.

Estimates differ between sources: the NDC gives 1.2% and the first transparency report 1.74%, with no year.

After the NDC was submitted in November 2025, phase 1 of the Shams Basra plant at Ratawi started running at 250 MW in May 2026, according to a project official quoted by Shafaq News, the first large solar capacity added since the pledge.

We therefore see progress, Satellite imagery shows the project's panels built on its site between December 2024 and October 2026, though imagery cannot show the operating capacity.

The confidence is «possible» because the pledge is measured by renewables’ share of generation, for which there are no 2026 data yet.

Project ledger

How much solar and wind capacity actually runs on Iraq’s grid, and how much does it add towards 8.5% of power generation by 2030?

250 MWCompleted after the NDC was submitted according to saved sources: 250 MW in 1 project.

How do we count?

The pledge is measured as a share of generation, but that share moves only as large plants are built and connected. So we record each plant with its capacity, status and source, and leave the share itself to Ember data.

Only capacity running on the grid after the NDC of 13 November 2025, with a saved source, counts towards the total. What started before then is the starting point; announcements, contracts and plants under construction are listed separately and not added. Iraq has no contracted wind project so far.

Counted 1 project
ProjectCapacityStatusStatus dateSatellite imagerySources
Shams Basra at Ratawi, phase 1

Phase 1 was connected to the grid in February 2026; the ministry said in March that 61 MW of it had started, and a project official said in May it runs at 250 MW.

250 MW operating 11 May 2026 confirmed on imagery
3 sources
Not counted yet 6 projectsunder construction 2agreement or memorandum 2announced 2
ProjectCapacityStatusStatus dateSources
Shams Basra, phases 2 to 4

Phase 2 was due in July 2026; we have found nothing yet confirming it runs. Completion is planned for 2028.

750 MW under construction 11 May 2026
2 sources
Iskandariya solar plant, Babil (Al-Bilal Group)

The investment licence was signed in April 2025; we found no opened source confirming construction.

225 MW agreement or memorandum 23 April 2025 Iraq Business News: Al-Bilal Group signs investment licences for 525 MW solar projects (23 Apr 2025)
Samawah solar plant (PowerChina)

The headline says “planned” while the text says work is under way to speed up construction; no completion date is given.

750 MW under construction 15 September 2026 Iraq Business News: 750MW solar plant planned for Samawah (15 Sep 2026)
Najaf solar plant (ACWA Power)

Contracting was under way in April 2025; we found no opened source confirming a signed contract.

1000 MW announced 29 April 2025 Iraq Business News: Iraq and ACWA advance Najaf solar power plant (29 Apr 2025)
Masdar plants in Maysan, Dhi Qar and Anbar

Power purchase talks were under way in May 2025; we found no opened source confirming signature.

1000 MW announced 5 May 2025 Shafaq News: Iraq pushes for renewables with UAE energy deal (5 May 2025)
Three plants in Erbil, Sulaymaniyah and Duhok

The report names neither the developers nor a commissioning date.

350 MW agreement or memorandum 10 January 2025 Shafaq News: Solar power in Erbil villages (10 Jan 2025)
Starting point Completed before the NDC (the starting point, not counted as progress) · 1 project
ProjectCapacityStatusStatus dateSatellite imagerySources
Karbala solar plant (Al-Bilal Group), phase 1

Started in September 2025, before the NDC, so it is the starting point. We have found no later output figure yet.

22 MW / 300 operating 22 September 2025 confirmed on imagery
2 sources
What satellite imagery shows 2 projects

Shams Basra at Ratawi, phase 1

Shams Basra at Ratawi, phase 1: Before and after construction, Sentinel-2 imagery
Before and after construction

Left: 10 December 2024; right: 16 October 2026. The yellow line is the site outline from a saved source.

Solar panels fill the whole mapped project site, and extend beyond it, in Sentinel-2 imagery of 16 October 2026; the site was empty on 10 December 2024. This confirms the plant was built but not its capacity, because the mapped site covers the whole 1,000 MW project.

Karbala solar plant (Al-Bilal Group), phase 1

Karbala solar plant (Al-Bilal Group), phase 1: Before and after construction, Sentinel-2 imagery
Before and after construction

Left: 27 October 2024; right: 11 November 2026. The yellow line is the site outline from a saved source.

A solar array appears at the mapped site, extending slightly north of it, in imagery of 11 November 2026; the site was empty on 27 October 2024. The image does not show whether the plant reached 75 MW.

Contains modified Copernicus Sentinel-2 data; site outlines from OpenStreetMap. Imagery confirms construction, not capacity or operation.

How we monitor this pledge

Next review · 31 March 2027

Required path

12/20240.287%12/20308.5%
  • Required path
  • Half the required pace

On 19 November 2026 the straight line requires 2.9%; progress counts as seen at 1.6% or above, half the required pace.

Indicator
Solar and wind’s share of total electricity generation, to test the 8.5% target in 2030.
Unit
Per cent.
Share of
Total Iraqi electricity generation in the same series and year.
Baseline
In Ember’s 2024 series, solar provided 0.287% and wind 0%. Use their sum in that series as the pre-pledge pace reference, subject to generation coverage. The all-renewables share including hydropower covers a wider set of sources.
What counts as a completed output
A solar or wind plant that entered service after counting began with documented operating capacity, or a published annual generation share for both sources during the monitoring period. Test the final target using actual generation.

Where we follow it

  • Project ledgerMain route

    The pledge ledger and its saved evidence for the commissioning dates and operating capacity of solar and wind plants.

  • Published data

    Ember annual data and Iraqi electricity generation tables when published. Sum solar and wind output and divide by total generation in the same series.

  • Satellite imagery

    Before-and-after Sentinel-2 imagery to verify that a facility exists. Operating records are needed to confirm commissioning and capacity.

Proxy

Operating megawatts in the ledger stand in for generation share. Do not convert them into a share without measured electricity output.

We measure something close to the indicator, not the indicator itself, so confidence is “Possible” at most.

Next review 31 March 2027

Sources we watch, and why8 sources
  • وزارة الكهرباء العراقية · official · manual
    Signs power purchase agreements and announces grid connection and capacity. The site refuses automated reading.
  • مكتب رئيس الوزراء · official · manual
    The Prime Minister opens plants in person, as in Karbala, and states their capacity on the day. The site refuses automated reading.
  • Iraq Business News · secondary · automatic
    Carries ministry statements on solar projects with their official source; its RSS feed works.
  • شفق نيوز · local · automatic
    Reports statements by project officials in the provinces, including the first operating phase of Shams Basra.
  • روداو · local · automatic
    Covers Kurdistan Region projects that do not appear in federal Ministry of Electricity statements.
  • بيانات الشركات (TotalEnergies وACWA Power وMasdar وPowerChina ومجموعة البلال) · secondary · manual
    Developers announce contracts, financial close and commissioning, sometimes before the official announcement.
  • Ember: بيانات التوليد السنوية · data · manual
    The pledge itself is measured as a share of generation or demand, which Ember publishes yearly; we compare the capacity in this ledger against it.
  • صور Sentinel-2 (كوبرنيكوس) · verification · manual
    Solar fields show clearly on imagery, so we check a plant exists and its extent before counting it.

What’s new?

Government announcements we follow. What official bodies announce, as published. Not counted in the total until we check it.

Announcement: UnresolvedMinistry of Electricity · 15 September 2026 · We return to it: March 2027Construction of the Samawah solar plant is being sped up, in two phases of 250 and 500 MW.
Announcement: UnresolvedMinistry of Electricity · 4 March 2026 · Announced date: December 202861 MW of Shams Basra’s first unit has started, with the full 1,000 MW project due in 2028.
Announcement: Not keptPrime Minister’s Office · 22 September 2025 · announced date has passed: November 2025The Karbala solar plant began producing 22 MW and is expected to reach 75 MW within two months.