IraqIQ-06Electricity

Convert single-cycle to combined-cycle power plants, about 9 GW by 2030

Where does the pledge stand?

Too early to judge

It is therefore too early to judge the pledge, and we return to it when the first unit enters service.

20% of the time between the NDC and the deadline has passed.

Last updated: 18 November 2026What do the status and confidence mean?

What did the country pledge?

converting single-cycle to combined-cycle power plants (around 9 GW capacity by 2030)
From the English translation · Page: PDF 17 (printed 10)
Target
around 9 GW
Deadline
2030
Baseline before the pledge
The first transparency report lists planned additional capacity. Units operating before the pledge form the starting point. A pace line needs a separation of conversion capacity already in service from planned capacity and a match between the report’s scope and the target. How we monitor this pledge
Condition
The document does not say whether it is conditional
What we measure
The single-to-combined-cycle projects in the first transparency report’s list, and what reports published after the NDC say about their construction and completion.

How do we know?

  1. 1Iraq BTR1: list of combined-cycle projects (Tables 3-8 to 3-28)Document · 4 September 2025
  2. 2Xinhua: Euphrates combined-cycle add-on under construction in four provinces (625 MW)Open-source media · 25 November 2025
  3. 3Ministry of Electricity via Iraq Business News: South Baghdad and Khor al-Zubair units under constructionOpen-source media · 23 October 2026
  4. 4Prime Minister’s office via Iraq Business News: construction starts at Qayyarah combined-cycle plantOpen-source media · 18 July 2025
The full assessment

Iraq’s first BTR lists 21 projects to expand combined-cycle plants and convert single-cycle plants, which it says add 8,789 MW between 2021 and 2030.

Reports published after the NDC was submitted in November 2025 confirm construction continuing on six of them, 875 MW in all: four Shanghai Electric projects in Najaf, Karbala, Babylon and Qadisiyah (625 MW) and two Dongfang Electric units at South Baghdad and Khor al-Zubair (250 MW), due before summer 2027.

The 375 MW Qayyarah plant has been under construction since July 2025.

We found no conversion unit completed since the pledge, and the BTR says phase 2 of two other projects was halted for lack of funding.

Under our rule, construction alone is not progress: progress needs capacity completed and running.

It is therefore too early to judge the pledge, and we return to it when the first unit enters service.

Project ledger

How many single-cycle plants have actually been converted to combined cycle since the NDC, and how much capacity do they add towards about 9 GW by 2030?

0 MWIn the saved sources we have not yet found anything completed after the NDC was submitted.

Official aggregate figuresNot added to the total
How do we count?

The pledge is met not by one decision but by the 21 plants listed in Iraq’s first transparency report. So we follow each plant, recording its status as the government gives it and then what later reports say.

Only plants completed and running after the NDC of 13 November 2025, with a saved source, count towards the total. Plants completed before that are the starting point and are listed separately. We do not turn “phase 1 completed” into megawatts unless the source gives the capacity. The capacities in the table add up to 8,140 MW, less than the 8,789 MW the report states; the report does not explain the difference.

Counted no projects

Not counted yet 19 projectshalted 2under construction 17
ProjectCapacityStatusStatus dateSources
Samawah and Dhi Qar stations

The BTR says phase 1 is completed and phase 2 halted for lack of funding, but not which capacity was completed, so we count none of it.

500 MW halted 4 September 2025 Iraq Biennial Transparency Report
Basmaya investment project

The BTR describes phases 1 and 2 as 1,000 MW and phase 3 as 500 MW, and says phase 1 is completed and phase 2 halted for lack of funding, so the completed capacity is unknown and we count none of it.

1500 MW halted 4 September 2025 Iraq Biennial Transparency Report
Rumaila investment station

Status as given in the first transparency report; no later report found yet.

1000 MW under construction 4 September 2025 Iraq Biennial Transparency Report
Rumaila gas units conversion

Status as given in the first transparency report; no later report found yet.

1000 MW under construction 4 September 2025 Iraq Biennial Transparency Report
Kirkuk gas station

Status as given in the first transparency report; no later report found yet.

278 MW under construction 4 September 2025 Iraq Biennial Transparency Report
Diwaniyah gas station

Xinhua names four provinces and 625 MW, not the stations. We link this station to the report because the four stations’ capacities in the BTR add up to exactly 625 MW.

250 MW under construction 25 November 2025
2 sources
Mansuriyah gas station

Status as given in the first transparency report; no later report found yet.

364 MW under construction 4 September 2025 Iraq Biennial Transparency Report
Al-Hilla gas station

Xinhua names four provinces and 625 MW, not the stations. We link this station to the report because the four stations’ capacities in the BTR add up to exactly 625 MW.

125 MW under construction 25 November 2025
2 sources
Khor al-Zubair gas station

The Ministry of Electricity said in October 2026 that the unit is under construction and due before summer 2027, and that equipment held up in the Strait of Hormuz delayed the work.

125 MW under construction 23 October 2026
2 sources
Karbala gas station

Xinhua names four provinces and 625 MW, not the stations. We link this station to the report because the four stations’ capacities in the BTR add up to exactly 625 MW.

125 MW under construction 25 November 2025
2 sources
Najaf gas station

Xinhua names four provinces and 625 MW, not the stations. We link this station to the report because the four stations’ capacities in the BTR add up to exactly 625 MW.

125 MW under construction 25 November 2025
2 sources
Shadra 1 and 2 gas stations

Name as spelled in the English report; we have not confirmed the Arabic name. Capacity is both stations, 160 and 169 MW.

329 MW under construction 4 September 2025 Iraq Biennial Transparency Report
Haditha 1 gas station

Status as given in the first transparency report; no later report found yet.

250 MW under construction 4 September 2025 Iraq Biennial Transparency Report
Al-Quds 3 gas station

The BTR lists this project twice with the same text, so we count it once. No later report found yet.

250 MW under construction 4 September 2025 Iraq Biennial Transparency Report
Al-Khairat gas station

Status as given in the first transparency report; no later report found yet.

625 MW under construction 4 September 2025 Iraq Biennial Transparency Report
Qayyarah gas station

The Prime Minister launched construction in July 2025, before the NDC. The BTR gives a total of 750 MW after conversion; the news report says 1,125 MW.

375 MW under construction 18 July 2025
2 sources
Akkas gas station

Status as given in the first transparency report; no later report found yet.

125 MW under construction 4 September 2025 Iraq Biennial Transparency Report
Debis gas station

The BTR mislabels this as "Project 5". No later report found yet.

169 MW under construction 4 September 2025 Iraq Biennial Transparency Report
South Baghdad 1 gas station

The Ministry of Electricity said in October 2026 that the unit is under construction and due before summer 2027, and that equipment held up in the Strait of Hormuz delayed the work.

125 MW under construction 23 October 2026
2 sources
Starting point Completed before the NDC (the starting point, not counted as progress) · 2 projects
ProjectCapacityStatusStatus dateSatellite imagerySources
Maysan station

Implemented according to the transparency report published before the NDC; the report gives no completion date.

250 MW operating — not yet checked on imagery Iraq Biennial Transparency Report
Al-Amara station

Implemented according to the transparency report published before the NDC; the report gives no completion date.

250 MW operating — not yet checked on imagery Iraq Biennial Transparency Report

How we monitor this pledge

Next review · 30 June 2027
Indicator
Operating capacity actually added by converting single-cycle units to combined cycle. Separate conversion additions from existing capacity and new plants with no conversion.
Unit
Megawatts of added capacity, shown in gigawatts for comparison with the target.
Baseline
The first transparency report lists planned additional capacity. Units operating before the pledge form the starting point. A pace line needs a separation of conversion capacity already in service from planned capacity and a match between the report’s scope and the target.
What counts as a completed output
A converted unit generating in service after counting began, with documented incremental capacity. Planned capacity, contracts and construction stay outside the total.

Where we follow it

  • Project ledgerMain route

    The pledge ledger based on the combined-cycle project tables in the first transparency report, tracking each unit’s added capacity and operating date.

  • Dedicated investigation

    Ministry of Electricity or operator handover and grid-connection records, cross-checked against contractor or press reporting for the same unit to avoid double counting.

Next review 30 June 2027

Sources we watch, and why8 sources
  • وزارة الكهرباء العراقية · official · manual
    The executing body for every project; it announces unit commissioning and progress meetings with contractors. The site refuses automated reading, so we read it by hand.
  • مكتب رئيس الوزراء · official · manual
    The Prime Minister opens plants and construction work in person, as at Qayyarah. The site refuses automated reading.
  • وكالة الأنباء العراقية (واع) · official · manual
    The official agency carries Ministry of Electricity statements and output figures. The site refuses automated reading.
  • Iraq Business News · secondary · automatic
    Translates ministry and Prime Minister’s Office statements and names the official source in each item; its RSS feed works.
  • شفق نيوز · local · automatic
    A local outlet covering the provinces; it reports outages and project delays that official statements usually leave out.
  • شينخوا وبوابة الحزام والطريق · secondary · manual
    Chinese firms build most of the combined-cycle projects, and the Chinese agency reports their progress from the sites.
  • بيانات الشركات المنفذة (Shanghai Electric وDongfang وArgan وGE وSiemens) · secondary · manual
    Contractors announce unit completion and handover in press releases and investor reports, sometimes before the official announcement.
  • صور Sentinel-2 (كوبرنيكوس) · verification · manual
    New heat-recovery boilers and stacks appear beside the gas units, so we check construction exists before counting any plant.

What’s new?

Government announcements we follow. What official bodies announce, as published. Not counted in the total until we check it.

Announcement: UnresolvedMinistry of Electricity · 23 October 2026 · Announced date: June 2027The 125 MW combined-cycle units at South Baghdad and Khor al-Zubair are under construction and will enter service before next summer.
Announcement: UnresolvedPrime Minister’s Office · 18 July 2025 · We return to it: January 2027Construction launched on the Qayyarah combined cycle, adding 375 MW.