Launch a public digital platform for short-lived climate pollutant emissions by 2027

Where does the pledge stand?

Too early to judge

A tender is a step that has produced nothing yet, so under our rule it is not progress; it is too early to judge, and we return to it when the award is announced or the platform launches.

48% of the time between the NDC and the deadline has passed.

Last updated: 18 November 2026What do the status and confidence mean?

What did the country pledge?

Build digital SLCP platform for emissions with public access
From the English translation · Page: PDF 21 (printed 14)

In the target column of the same table: «Platform live by 2027»

Deadline
2027
Baseline before the pledge
The NDC names the platform and its launch deadline without documenting an existing platform. UNDP published a tender for a monitoring, reporting and verification platform; pollutant coverage and public access still need confirmation. This is a single deliverable tested at launch. How we monitor this pledge
Condition
The document does not say whether it is conditional
What we measure
Whether a public online platform for short-lived climate pollutant emissions exists by 2027, and what data it publishes.

How do we know?

  1. 1UNDP: tender for the design of Iraq’s national MRV framework and digital platform (UNDP-IRQ-02201)Document · 23 August 2026
The full assessment

We found one step since the NDC: on 23 August 2026 UNDP Iraq published a tender for the “Design of Iraqi’s National MRV Framework and digital platform, with operationalization for the energy sector”, which closed on 26 September 2026 with no award shown.

But the tender mentions neither short-lived climate pollutants nor public access, the core of the pledge.

A tender is a step that has produced nothing yet, so under our rule it is not progress; it is too early to judge, and we return to it when the award is announced or the platform launches.

How we monitor this pledge

Next review · 31 March 2027
Indicator
Public availability of an operational digital platform that shows short-lived climate pollutant emissions data.
Unit
One functioning, testable platform.
Baseline
The NDC names the platform and its launch deadline without documenting an existing platform. UNDP published a tender for a monitoring, reporting and verification platform; pollutant coverage and public access still need confirmation. This is a single deliverable tested at launch.
What counts as a completed output
A working public link giving access to actual short-lived pollutant emissions data. An award, internal platform or launch announcement alone is insufficient.

Where we follow it

  • Dedicated investigationMain route

    Search the portals of the Iraqi agencies responsible for emissions, open the published link and test the data and access without a restricted account.

  • Government announcements

    UNDP award notices, handover records and operator announcements to locate the platform and establish its scope.

Next review 31 March 2027