Five landfill methane capture pilot sites by 2028

Where does the pledge stand?

Too early to judge

We found a lead that is not enough to judge.

32% of the time between the NDC and the deadline has passed.

Last updated: 18 November 2026What do the status and confidence mean?

What did the country pledge?

Implement landfill methane capture pilots
From the English translation · Page: PDF 21 (printed 14)

In the target column of the same table: «5 pilot sites by 2028»

Target
5 pilot sites
Deadline
2028
Baseline before the pledge
Start the count of newly completed pilots at zero on submission. The ledger identifies a system at Kani Qirzhala landfill, but its operating date and actual capture need documentation before the site can count. How we monitor this pledge
Condition
The document does not say whether it is conditional
What we measure
Landfill methane capture sites operating or under way, as reported officially and in the news.

How do we know?

  1. 1KirkukNow: Erbil drills 250 gas wells at the Kani Qirzhala landfillOpen-source media · 6 May 2026
  2. 2Global NEST Journal: greenhouse gas emissions from Erbil City landfill (17 July 2026)Document · 17 July 2026
The full assessment

We found a lead that is not enough to judge.

Erbil’s Director of Services and Environmental Protection told KirkukNow on 6 May 2026 that the administration introduced a Japanese system that “involves drilling 250 gas wells at the Kani Qirzhala landfill to capture gas produced by decomposing waste”.

But the report says neither when this began nor whether the wells work.

A study of the same Erbil landfill published in the Global NEST Journal on 17 July 2026 recommends “prioritizing active gas collection infrastructure”, so it does not treat one as in place.

We do not count the report as progress until we find a site confirmed to be working after the NDC, so it is too early to judge the pledge.

Project ledger

How many landfill methane capture sites actually operate in Iraq, and how far is that from five pilot sites by 2028?

0 sitesIn the saved sources we have not yet found anything completed after the NDC was submitted.

How do we count?

The NDC counts five sites but does not name them, so the pledge can only be checked site by site. We record each announced site with its status and source.

A site counts only if a saved source says it actually captures gas after the NDC of 13 November 2025. An announced system, plan or study is listed separately and not counted.

Counted no projects

Not counted yet 1 projectannounced 1
ProjectSitesStatusStatus dateSources
Kani Qirzhala landfill, Erbil

The Director of Services and Environmental Protection said a Japanese system with 250 wells was introduced, but not when or whether the wells work. A study published in July 2026 recommends building gas collection, so it does not treat one as in place.

1 sites announced 6 May 2026
2 sources

How we monitor this pledge

Next review · 31 March 2027

Required path

sites

11/2025012/20285
  • Required path
  • Half the required pace

On 19 November 2026 the straight line requires 1.6 sites; progress counts as seen at 0.8 sites or above, half the required pace.

Indicator
Number of pilot landfill sites with operating waste-methane capture during the counting period.
Unit
Distinct pilot sites.
Baseline
Start the count of newly completed pilots at zero on submission. The ledger identifies a system at Kani Qirzhala landfill, but its operating date and actual capture need documentation before the site can count.
What counts as a completed output
One landfill with a system verified to collect waste gas after counting began. Wells are not counted separately; drilling and installation do not count before operation.

Where we follow it

  • Project ledgerMain route

    The pledge ledger, using municipal or operator documents naming each site and showing commissioning and gas capture.

  • Dedicated investigation

    Engineering reports, independent studies and local reporting to check whether the collection system is running at the site and when it started.

Next review 31 March 2027

Sources we watch, and why7 sources
  • وزارة البيئة العراقية · official · automatic
    Responsible for the NDC and transparency reports; announces waste and methane projects funded by international partners.
  • هيئة البيئة في إقليم كردستان ومديريات البلديات · official · manual
    The only site found so far is in Erbil, run by regional and municipal authorities rather than the federal government.
  • كركوك ناو · local · manual
    A local outlet covering environment and waste in the north; it carried the report of gas wells at the Kani Qirzhala landfill.
  • روداو · local · automatic
    Covers decisions of the regional government and municipalities, where any site in Kurdistan is likely to be announced.
  • Iraq Business News · secondary · automatic
    Publishes government tenders and contracts, including waste treatment and waste-to-energy contracts.
  • الدراسات المحكّمة عن مكبات العراق · secondary · manual
    Field studies describe landfill conditions, as the Global NEST study of the Erbil landfill did, and show whether a capture system is in place.
  • صور Sentinel-2 (كوبرنيكوس) · verification · manual
    Gas wells, their pipe network and the flare show on the landfill, so we check they exist before counting any site.

What’s new?

Government announcements we follow. What official bodies announce, as published. Not counted in the total until we check it.

Announcement: UnresolvedErbil Director of Services and Environmental Protection · 6 May 2026 · We return to it: January 2027The administration introduced a Japanese system involving 250 gas wells at the Kani Qirzhala landfill.
Our side
not yet checkedA study published in July 2026 recommends building gas collection, so it does not treat one as in place.