Cut electricity transmission and distribution losses to about 10% by 2050

Where does the pledge stand?

Too early to judge

The NDC was submitted in November 2025, so we do not rate the pledge until data for 2026 onward are available.

4% of the time between the NDC and the deadline has passed.

Last updated: 18 November 2026What do the status and confidence mean?

What did the country pledge?

Reducing electricity transmission and distribution losses gradually to reach up to 10% only by 2050 and improving power generation efficiency.
From the English translation · Page: PDF 17 (printed 10)
Target
losses of about 10%
Deadline
2050
Baseline before the pledge
according to the World Bank, transmission and distribution losses were 58.7% of electricity output in 2024, including, by the World Bank’s definition, pilferage. Sources
Condition
The document does not say whether it is conditional
What we measure
Transmission and distribution losses in World Bank data and Ministry of Electricity reports, separating technical and commercial losses.
Note from the document
The NDC puts current grid efficiency at about 50% (Arabic original, p. 14).

How do we know?

  1. 1World Bank: electric power transmission and distribution losses in Iraq (% of output)Dataset · 11 November 2026
  2. 2Iraq Biennial Transparency Report
The full assessment

Baseline before the pledge: according to the World Bank, transmission and distribution losses were 58.7% of electricity output in 2024, including, by the World Bank’s definition, pilferage.

The first transparency report gives 22%, most likely technical losses only.

The NDC was submitted in November 2025, so we do not rate the pledge until data for 2026 onward are available.

How we monitor this pledge

Next review · 30 June 2027

Required path

12/202022%12/205010%
  • Required path
  • Half the required pace

On 19 November 2026 the straight line requires 19.6%; progress counts as seen at 20.8% or below, half the required pace.

Indicator
The share of electricity lost in transmission and distribution, distinguishing technical from commercial losses where sources allow.
Unit
Per cent.
Share of
Total electricity output within the scope and period, or the denominator specified by the official series with the difference documented.
Baseline
Iraq’s first transparency report sets a 2020 transmission and distribution loss baseline of 22% for the same pathway that targets 10% by 2050. The pace line connects these two values. The World Bank’s 58.7% figure for 2024 includes pilferage and is a comparison point within its own series.
What counts as a completed output
A published annual loss value after counting began with a comparable method that specifies network boundaries and treatment of commercial losses. Meter installation and grid repairs alone do not demonstrate a fall in national losses.

Where we follow it

  • Published dataMain route

    The Ministry of Electricity’s annual power balance and transparency reports: match loss definitions, grid scope and generation and delivery periods.

  • Published data

    The World Bank indicator for transmission and distribution losses as a share of output, for comparison within its definition that includes pilferage.