PaxMemoriaPledgeMeter Methodology

LebanonLB-03Renewable energy

Renewables meet 25% of electricity demand by 2035

Where does the pledge stand?

Implementation progress · Progress seen

The Siblin solar system was inaugurated on 4 December 2025. On 2 February 2026 UNRWA confirmed that it supplied the training centre and two schools. The reported 1,180 kWp covers several Lebanese sites. Siblin’s own capacity is unknown.

Pace towards the target · Cannot yet be assessed

The latest published national share was 12.8% of demand in 2024, before Siblin entered service. Assessing the pace towards 25% by 2035 requires renewable generation and total national electricity demand for the same period after commissioning.

11% of the time between the NDC and the deadline has passed.

Last updated: 19 November 2026What do the status and confidence mean?

What did the country pledge?

25% of the power demand (i.e. electricity demand) in 2035 is generated by renewable energy sources.
Page: PDF 22
Target
25% of electricity demand
Deadline
2035
Baseline before the pledge
The NDC says renewables’ share of electricity demand reached 12.1% in 2022. The National Renewable Energy Action Plan gives 12.3% for 2023 and 12.8% for 2024, the last value published before counting started on 30 September 2025. The required-pace line starts from the NDC’s 2022 value on 31 December 2022 and runs to 31 December 2035. How we monitor this pledge
Condition
No condition
What we measure
Renewables’ share of electricity demand in official figures: the National Renewable Energy Action Plan and the transparency reports. Ember data are shown for comparison only, because they measure the share of grid generation, not the share of demand, much of which private generators supply.
Note from the document
The NDC says achieving its targets “is contingent on the implementation of key cross-cutting enablers”: legislation, regulatory and economic instruments, finance mechanisms, green technologies and local skills (p. 23). Even the unconditional target therefore depends on these domestic conditions.

How do we know?

  1. 1Embassy of Japan in Lebanon — inauguration date of the Siblin solar systemDocument · 8 December 2025
  2. 2UNRWA — electricity supplied at Siblin and total project capacity in LebanonDocument · 2 February 2026
  3. 3National Renewable Energy Action Plan — renewables’ share of demand through 2024, Table 4Document · 2025
  4. 4Ember yearly electricity generation dataDataset · 2026
  5. 5Lebanon Biennial Transparency Report
  6. 6النهار: 165 ميغاواط شمسية و226 ميغاواط من الرياح، رخص تنتظر التمويل (17 أيلول/سبتمبر 2026)
  7. 7pv magazine: Lebanon tenders 350 MW of solar (27 Jul 2026)
  8. 8pv magazine: Lebanon inks three PPAs for 45 MW of solar (25 Sep 2025)
The full assessment

The solar system at the Siblin Training Centre was inaugurated on 4 December 2025, after Lebanon submitted its NDC on 30 September.

On 2 February 2026 UNRWA confirmed that the system supplied electricity to the centre and two neighbouring schools.

UNRWA reported a total peak capacity of 1,180 kWp across the Japanese-funded project’s sites in Lebanon.

Renewables’ share of national electricity demand after the Siblin system entered service is still unknown, so it is too early to judge the pace towards the 25% target.

Calculating that share requires renewable electricity generation from all sources and total electricity demand in Lebanon for the same period.

The latest published value is 12.8% for 2024, according to the National Renewable Energy Action Plan, against 12.1% for 2022 in the NDC.

The required-pace line starts at 12.1% on 31 December 2022 and ends at 25% on 31 December 2035; the 2024 value was below half that pace, and the 2024 value serves as a reference from before counting began.

The ledger holds the 11 solar licences and the three Akkar wind licences of 226 MW, and none of them has entered service.

The action plan says all 11 solar projects are delayed for lack of financing, and their deadline to meet the conditions was extended to 31 December 2026.

The wind licences have not moved to implementation because their holders could not secure financing; the source mentions no extension for them, only that one can be requested.

In September 2026 the Electricity Regulatory Authority said the Merit group had met all requirements and planned to lay the foundation stone within two months, that is in November 2026; we are following this announcement.

pv magazine reports IRENA figures putting Lebanon’s cumulative solar capacity at 1,505 MW at the end of 2025, but the series is inconsistent: the same outlet gave 1,005 MW from IRENA for the end of 2024 in September 2025, then 1,081 MW for the same date in July 2026.

The figure does not separate what was installed after 30 September 2025.

Project ledger

How much large renewable capacity actually runs in Lebanon, and how much does it add towards 25% of electricity demand by 2035, or 30% with extra grants?

0 MWIn the saved sources we have not yet found anything completed after the NDC was submitted.

Official aggregate figuresNot added to the total
How do we count?

Most growth so far has come from distributed rooftop panels, which show in aggregate figures rather than projects. The large plants were licensed years ago and not built. So we record each licence and tender with its status, next to the official aggregate figures.

Only capacity running after the NDC of 30 September 2025, with a saved source, counts towards the total. Licences, power purchase agreements and tenders are listed separately and not added. The same ledger serves LB-03 and LB-04, which depend on the same projects.

Counted no projects

Not counted yet 7 projectsagreement or memorandum 5announced 2
ProjectCapacityStatusStatus dateSources
Three solar licences held by CMA CGM (Merit Invest)

Power purchase agreements were signed in September 2025. In September 2026 the regulator said the group had met all requirements and planned to lay the foundation stone within two months.

45 MW agreement or memorandum 25 September 2025
2 sources
Solar licence in South and Nabatieh (PrimeSouth)

The cabinet transferred the licence to the company on 9 October 2025.

15 MW agreement or memorandum 8 December 2025 Crédit Libanais Economics: solar licence transferred to PrimeSouth (8 Dec 2025)
C.D.N and EONE solar projects

Two amended power purchase agreements were signed in October 2026.

30 MW agreement or memorandum 8 October 2026 منصة الطاقة: الطاقة الشمسية في لبنان تنتعش باتفاقيتين (8 تشرين الأول/أكتوبر 2026)
The other five solar licences

What remains of the 11 licences signed in 2023 after those listed above; we worked this out by subtraction and have not confirmed it. They are delayed for lack of financing, and the deadline was extended to end-2026.

— agreement or memorandum 8 May 2023
3 sources
Akkar wind farms (round 1)

Contracts signed in 2018 with completion expected by end-2022; construction has not started for lack of financing.

226 MW agreement or memorandum 1 February 2018
2 sources
Regulator’s tender: five solar projects with storage

The tender is at the expressions-of-interest stage; sites and winners are not published.

350 MW announced 27 July 2026 pv magazine: Lebanon tenders 350 MW of solar (27 Jul 2026)
QatarEnergy and TotalEnergies solar plant

Announced with no capacity, site or contract.

— announced 16 October 2026 The National: Qatar pledges to help modernise Lebanon’s energy sector (16 Oct 2026)

How we monitor this pledge

Next review · 15 January 2027

Required path

12/202212.1%12/203525%
  • Required path
  • Half the required pace

On 19 November 2026 the required path reaches 16%, and the half-pace benchmark is 14%. These are reference values for comparison when a national measurement becomes available.

Indicator
The share of electricity demand generated from renewable sources. In Lebanon these include hydropower, solar power and landfill gas.
Unit
Per cent of electricity demand, calculated from electricity generated (GWh), not installed capacity.
Share of
Total electricity demand in GWh, including what private generators supply when generation capacity falls short, not public-grid generation alone.
Baseline
The NDC says renewables’ share of electricity demand reached 12.1% in 2022. The National Renewable Energy Action Plan gives 12.3% for 2023 and 12.8% for 2024, the last value published before counting started on 30 September 2025. The required-pace line starts from the NDC’s 2022 value on 31 December 2022 and runs to 31 December 2035.
What counts as a completed output
For implementation we count a renewable installation that entered service after 30 September 2025 when a saved source documents generation and supply to users or the grid. We record site capacity when available and also track official increases in distributed capacity for periods starting after that date. To assess pace we use renewables’ share of national demand for a period after counting began.

Where we follow it

  • Published dataMain route

    Official figures for renewables’ share of electricity demand published by the Ministry of Energy and Water and the Lebanese Center for Energy Conservation, including the National Renewable Energy Action Plan, and the transparency reports that track the same indicator.

  • Project ledger

    The pledge’s project ledger, shared by LB-03 and LB-04: large plants that enter service after 30 September 2025, each with a saved source giving its capacity. The ledger records megawatts; a judgement on it alone would rest on a proxy for the share of demand, with confidence possible at most.

  • Published data2 sources
    • Aggregate installed solar capacity from the Lebanese Center for Energy Conservation and IRENA, because most growth comes from distributed rooftop panels, which do not show project by project.
    • Ember yearly electricity generation data, for comparison only, because they measure the share of grid generation, not the share of demand, much of which private generators supply.
  • Satellite imagery

    Sentinel-2 imagery to check that large plants stand at their sourced locations, before and after construction.

  • Government announcements

    Government announcements on licences, contracts, tenders and completion dates, shown and not counted until checked.

Next review 15 January 2027

Sources we watch, and why9 sources
  • وزارة الطاقة والمياه · official · manual
    Signs power purchase agreements with licence holders and announces deadline extensions and licence transfers.
  • المركز اللبناني لحفظ الطاقة (LCEC) · official · manual
    Publishes the national renewable energy action plan and official installed capacities, including distributed solar.
  • الهيئة الناظمة لقطاع الكهرباء · official · manual
    Launched a 2026 tender for five solar projects with storage; it will announce the winners.
  • الوكالة الوطنية للإعلام · official · automatic
    Publishes cabinet decisions, licence transfers and contract signings; its RSS feed works.
  • النهار · local · manual
    Follows the state and deadlines of the solar and wind licences, pulling together scattered official decisions.
  • منصة الطاقة · secondary · manual
    Tracks power purchase agreements in Lebanon and gives each project’s planned capacity.
  • pv magazine · secondary · manual
    Covers tenders, contracts and installed capacity in Lebanon, and carries IRENA figures.
  • Ember: بيانات التوليد السنوية · data · manual
    The pledge itself is measured as a share of generation or demand, which Ember publishes yearly; we compare the capacity in this ledger against it.
  • صور Sentinel-2 (كوبرنيكوس) · verification · manual
    Solar fields show clearly on imagery, so we check a plant exists and its extent before counting it.

What’s new?

Government announcements we follow. What official bodies announce, as published. Not counted in the total until we check it.

Announcement: UnresolvedPrime Minister of Qatar · 16 October 2026 · We return to it: April 2027QatarEnergy and TotalEnergies agreed to develop a solar plant in Lebanon as an initial project.
Announcement: UnresolvedElectricity Regulatory Authority, as reported by Annahar · 17 September 2026 · Announced date: November 2026Merit, part of CMA CGM, has met all requirements and plans to lay the foundation stone within two months.