LebanonLB-04Renewable energy
Renewables meet 30% of electricity demand by 2035, with additional grants
Where does the pledge stand?
A full year has passed since the NDC was submitted on 30 September 2025, and in that time we found no new renewable capacity that entered service with a saved source: this pledge uses the same project ledger as LB-03, and none of its projects has entered service.
11% of the time between the NDC and the deadline has passed.
Last updated: 18 November 2026What do the status and confidence mean?
What did the country pledge?
30% of the power demand (i.e. electricity demand) in 2035 is generated by renewable energy sources.
Original document: Lebanon's Nationally Determined Contribution NDC 3.0 – Target Year 2035
- Target
- 30% of electricity demand
- Deadline
- 2035
- Baseline before the pledge
- The NDC says renewables’ share of electricity demand reached 12.1% in 2022. The National Renewable Energy Action Plan gives 12.3% for 2023 and 12.8% for 2024, the last value published before counting started on 30 September 2025. The required-pace line starts from the NDC’s 2022 value on 31 December 2022 and runs to 31 December 2035. How we monitor this pledge
- Condition
- Conditional on international support
- What we measure
- Same indicator as LB-03.
How do we know?
- 1MEW and LCEC: National Renewable Energy Action Plan of Lebanon 2025–2030 (2025)
- 2Lebanon Biennial Transparency Report
The full assessment
A full year has passed since the NDC was submitted on 30 September 2025, and in that time we found no new renewable capacity that entered service with a saved source: this pledge uses the same project ledger as LB-03, and none of its projects has entered service.
But the official share of renewables in electricity demand has not yet been published for any year after the NDC, so the pledge stays “Too early to judge”.
The latest published value is 12.8% for 2024, according to the National Renewable Energy Action Plan, against 12.1% for 2022 in the NDC; the target is 30% in 2035 with additional international grants.
The required-pace line starts at 12.1% on 31 December 2022 and ends at 30% on 31 December 2035; the 2024 value was below half that pace, and this shortfall will enter the first judgement of the pledge.
The support state recorded for this pledge is “Too early to judge support”.
As long as the support is not recorded as arrived, we rate the pledge “Stalled” or “No visible progress” only on data that measure the share itself, or on satellite imagery.
Project ledger
How much large renewable capacity actually runs in Lebanon, and how much does it add towards 25% of electricity demand by 2035, or 30% with extra grants?
0 MWIn the saved sources we have not yet found anything completed after the NDC was submitted.
- 1190 MW Distributed solar capacity installed by end-2024 according to the national action plan, after deducting about 131 MW destroyed in the 2024 war (October 2025) · MEW and LCEC: National Renewable Energy Action Plan of Lebanon 2025–2030 (2025)
How do we count?
Most growth so far has come from distributed rooftop panels, which show in aggregate figures rather than projects. The large plants were licensed years ago and not built. So we record each licence and tender with its status, next to the official aggregate figures.
Only capacity running after the NDC of 30 September 2025, with a saved source, counts towards the total. Licences, power purchase agreements and tenders are listed separately and not added. The same ledger serves LB-03 and LB-04, which depend on the same projects.
Counted no projects
Not counted yet 7 projectsagreement or memorandum 5announced 2
| Project | Capacity | Status | Status date | Sources |
|---|---|---|---|---|
Three solar licences held by CMA CGM (Merit Invest)Power purchase agreements were signed in September 2025. In September 2026 the regulator said the group had met all requirements and planned to lay the foundation stone within two months. |
45 MW | agreement or memorandum | 25 September 2025 | |
Solar licence in South and Nabatieh (PrimeSouth)The cabinet transferred the licence to the company on 9 October 2025. |
15 MW | agreement or memorandum | 8 December 2025 | Crédit Libanais Economics: solar licence transferred to PrimeSouth (8 Dec 2025) |
C.D.N and EONE solar projectsTwo amended power purchase agreements were signed in October 2026. |
30 MW | agreement or memorandum | 8 October 2026 | منصة الطاقة: الطاقة الشمسية في لبنان تنتعش باتفاقيتين (8 تشرين الأول/أكتوبر 2026) |
The other five solar licencesWhat remains of the 11 licences signed in 2023 after those listed above; we worked this out by subtraction and have not confirmed it. They are delayed for lack of financing, and the deadline was extended to end-2026. |
— | agreement or memorandum | 8 May 2023 | |
Akkar wind farms (round 1)Contracts signed in 2018 with completion expected by end-2022; construction has not started for lack of financing. |
226 MW | agreement or memorandum | 1 February 2018 | |
Regulator’s tender: five solar projects with storageThe tender is at the expressions-of-interest stage; sites and winners are not published. |
350 MW | announced | 27 July 2026 | pv magazine: Lebanon tenders 350 MW of solar (27 Jul 2026) |
QatarEnergy and TotalEnergies solar plantAnnounced with no capacity, site or contract. |
— | announced | 16 October 2026 | The National: Qatar pledges to help modernise Lebanon’s energy sector (16 Oct 2026) |
How we monitor this pledge
Next review · 15 January 2027
Required path
- Required path
- Half the required pace
On 19 November 2026 the straight line requires 17.4%; progress counts as seen at 14.8% or above, half the required pace.
- Indicator
- The share of electricity demand generated from renewable sources. In Lebanon these include hydropower, solar power and landfill gas.
- Unit
- Per cent of electricity demand, calculated from electricity generated (GWh), not installed capacity.
- Share of
- Total electricity demand in GWh, including what private generators supply when generation capacity falls short, not public-grid generation alone.
- Baseline
- The NDC says renewables’ share of electricity demand reached 12.1% in 2022. The National Renewable Energy Action Plan gives 12.3% for 2023 and 12.8% for 2024, the last value published before counting started on 30 September 2025. The required-pace line starts from the NDC’s 2022 value on 31 December 2022 and runs to 31 December 2035.
- What counts as a completed output
- A published official value of renewables’ share of electricity demand for a year after counting started, beginning with 2026, or renewable capacity that entered service after 30 September 2025 with a saved source giving it, whether a plant in the ledger or an increase in the official distributed-capacity figure for a period starting after that date. Licences, power purchase agreements, tenders and projects under construction do not count.
Where we follow it
Published dataMain route
Official figures for renewables’ share of electricity demand published by the Ministry of Energy and Water and the Lebanese Center for Energy Conservation, including the National Renewable Energy Action Plan, and the transparency reports that track the same indicator.
Project ledger
The pledge’s project ledger, shared by LB-03 and LB-04: large plants that enter service after 30 September 2025, each with a saved source giving its capacity. The ledger records megawatts; a judgement on it alone would rest on a proxy for the share of demand, with confidence possible at most.
Published data2 sources
- Aggregate installed solar capacity from the Lebanese Center for Energy Conservation and IRENA, because most growth comes from distributed rooftop panels, which do not show project by project.
- Ember yearly electricity generation data, for comparison only, because they measure the share of grid generation, not the share of demand, much of which private generators supply.
Satellite imagery
Sentinel-2 imagery to check that large plants stand at their sourced locations, before and after construction.
Government announcements
Government announcements on licences, contracts, tenders and completion dates, shown and not counted until checked.
Next review 15 January 2027
Sources we watch, and why9 sources
- وزارة الطاقة والمياه · official · manual
Signs power purchase agreements with licence holders and announces deadline extensions and licence transfers. - المركز اللبناني لحفظ الطاقة (LCEC) · official · manual
Publishes the national renewable energy action plan and official installed capacities, including distributed solar. - الهيئة الناظمة لقطاع الكهرباء · official · manual
Launched a 2026 tender for five solar projects with storage; it will announce the winners. - الوكالة الوطنية للإعلام · official · automatic
Publishes cabinet decisions, licence transfers and contract signings; its RSS feed works. - النهار · local · manual
Follows the state and deadlines of the solar and wind licences, pulling together scattered official decisions. - منصة الطاقة · secondary · manual
Tracks power purchase agreements in Lebanon and gives each project’s planned capacity. - pv magazine · secondary · manual
Covers tenders, contracts and installed capacity in Lebanon, and carries IRENA figures. - Ember: بيانات التوليد السنوية · data · manual
The pledge itself is measured as a share of generation or demand, which Ember publishes yearly; we compare the capacity in this ledger against it. - صور Sentinel-2 (كوبرنيكوس) · verification · manual
Solar fields show clearly on imagery, so we check a plant exists and its extent before counting it.
What’s new?
Government announcements we follow. What official bodies announce, as published. Not counted in the total until we check it.
Announcement: UnresolvedQatarEnergy and TotalEnergies agreed to develop a solar plant in Lebanon as an initial project.
- Our side
- not yet checked
Announcement: UnresolvedMerit, part of CMA CGM, has met all requirements and plans to lay the foundation stone within two months.
- Our side
- not yet checked