Renewables at least 35% of electricity generation by 2035, with international support

Where does the pledge stand?

Too early to judge

It is too early to judge the pledge: as of 19 November 2026 we found in the saved sources no renewable plant or system that entered service since counting began on 1 January 2026 with a source giving its capacity.

0% of the time between the NDC and the deadline has passed.

Last updated: 19 November 2026What do the status and confidence mean?

What did the country pledge?

Central to this pillar is Yemen’s ambition to achieve at least 35% renewable energy share in total electricity generation by 2035.
Page: PDF 35 (printed 24)
Target
at least 35% of total electricity generation
Deadline
2035
Baseline before the pledge
the NDC gives no value for the renewable share in its 2022 base year. Sources
Condition
Conditional on international support
What we measure
Share of electricity generated from solar, wind and other renewables in total national generation, including public grid, off-grid and captive generation, as the NDC defines it. Ember and IRENA data under-count off-grid solar.
Note from the document
PDF page 35 calls the share an “ambition” and a “target”, and page 87 the “35% renewable-electricity target”. The ICTU annex says it is a supporting policy for the quantified target, not a separate NDC component, tracked as an implementation indicator (PDF p. 85), and a supporting non-GHG component of the conditional contribution that is not separately accounted (PDF p. 89). It is measured as electricity generated, not installed capacity (PDF p. 89).
Support the pledge depends on:Too early to judge supportThe contribution period began on 1 January 2026, and there are no data yet on the international support the target depends on.Support details are in the country profile.

How do we know?

  1. 1MEED: UAE firm withdraws Yemen solar operationsOpen-source media · 26 January 2026
  2. 2Yemen Eco: the electricity corporation approves technical measures to restore government service on the west coast, including completing the Khokha and Hays solar plants (headline only)Open-source media · 15 October 2026
  3. 3Express Tribune (Reuters): Solar energy brightens Middle East’s least electrified nationOpen-source media · 30 September 2025
  4. 4سبأ: رئيس الوزراء يشهد تدشين التشغيل الكلي لمحطة الطاقة الشمسية في عدن بقدرة 120 ميغاوات (15 تموز/يوليو 2024)
  5. 5سبأ: تدشين أول محطة كهرباء بالطاقة الشمسية بقدرة 53 ميجاوات في شبوة بدعم إماراتي (28 آب/أغسطس 2025)
  6. 6منصة الطاقة: الإمارات تسلم محطتي طاقة شمسية لليمن: "تعملان بكامل طاقتهما" (23 كانون الثاني/يناير 2026)
  7. 7وزارة الكهرباء والطاقة: وزير الكهرباء يوجّه بمعالجة الأعطال الفنية في محطة الطاقة الشمسية (21 شباط/فبراير 2026)
  8. 8سبأ: العمقي يدشن محطة الطاقة الشمسية العملاقة للشركة العربية اليمنية للأسمنت بقدرة 13.75 ميجاواط (27 تشرين الثاني/نوفمبر 2025)
  9. 9منصة الطاقة: أهم 5 مشروعات طاقة شمسية في اليمن.. محطات تعزز إمدادات الكهرباء (إنفوغرافيك) (14 آب/أغسطس 2025)
  10. 10pv magazine: Yemen’s largest solar plant set to double to 240 MW (8 Sep 2026)
  11. 11منصة الطاقة: واردات اليمن من الألواح الشمسية الصينية تقفز 83% في 6 أشهر (14 آب/أغسطس 2026)
The full assessment

It is too early to judge the pledge: as of 19 November 2026 we found in the saved sources no renewable plant or system that entered service since counting began on 1 January 2026 with a source giving its capacity.

Baseline before the pledge: the NDC gives no value for the renewable share in its 2022 base year.

We therefore start from the plants running before the contribution period: the 120 MW Aden solar plant, whose full operation was inaugurated on 15 July 2024; the 53 MW Shabwa plant, running since August 2025; phase 1 of the Mokha plant, whose capacity is still unresolved; the 40 MW Al-Hussein plant in Hodeidah; and a 13.75 MW captive plant at a cement works in Hadramawt.

In early 2026 the Aden plant’s output was below capacity because of faults, and Attaqa put it at about 80% of design capacity, although the operator said it handed the plant over running at full technical capacity.

In January 2026 five projects being built by a UAE company were paused when it left Yemen.

According to MEED, phase 2 of the Mokha plant was 85% complete, the Khokha plant 80%, the Hays plant 75%, the Socotra plant 35% and the Aden expansion 35%.

On 15 October 2026 the Public Electricity Corporation approved measures including completing the Khokha and Hays plants, according to a Yemen Eco headline, and we found nothing showing that any of the five projects entered service.

We could not check the running or halted plants on satellite imagery, because the sources name only areas and give no outline or coordinates for any plant.

Before counting began, IRENA put Yemen’s operational solar PV capacity at 456 MW at the end of 2025, as reported by pv magazine, and the International Energy Agency put solar at 10.4% of Yemen’s electricity generation in 2023, according to a Reuters report carried by the Express Tribune.

This is not the base-year value the NDC refers to.

Attaqa, citing Ember data, reports 750 MW of Chinese panel imports between January and June 2026, but imports are not completed plants, so these figures do not change the reason for the rating.

This is not a finding of no progress or of stalling: our rule allows neither before a full year after counting starts, that is, before 1 January 2027.

The pledge depends on international support for which there are no data yet, so we would call it stalled or not progressing only on measured data, and it is measured by the share of generation, for which there are no 2026 data.

We will look at the pledge again on 1 January 2027.

Project ledger

How much renewable capacity has actually started running in Yemen since the contribution period began, and what does it add towards at least 35% of electricity generation by 2035?

0 MWIn the saved sources we have not yet found anything completed since the contribution period began on 1 January 2026.

Official aggregate figuresNot added to the total
How do we count?

The pledge is broad: it is met by many plants, mini-grids and home systems, not by one decision. The NDC notes the rapid expansion of decentralised solar, which does not show project by project. So we record each plant, tender and agreement with its status and source, next to published aggregate figures.

Only capacity running since the contribution period began on 1 January 2026, ten months before the NDC was submitted on 9 November 2026, because the NDC itself sets that start date (PDF p. 85), with a saved source giving the capacity, counts towards the total. What was running before the period began is shown as the starting point, not counted as progress. Announcements, agreements, memoranda, tenders and projects under construction are listed separately and not added. Operating plants are checked on satellite imagery where possible. Megawatts are not the pledge’s measure: the NDC measures it as electricity generated, not installed capacity, covering public grid, off-grid and captive generation (PDF p. 89), so we do not turn the ledger total into a share. Annex IV of the NDC mentions around 2,800 MW of renewable capacity added by 2035 (PDF p. 96); we give the figure for comparison only, not as a separate target.

Counted no projects

Not counted yet 14 projectshalted 5announced 7agreement or memorandum 1under construction 1
ProjectCapacityStatusStatus dateSources
Aden solar plant expansion, phase 2

The phase adds 120 MW for a 240 MW total, with 30 MW of battery storage. The agreement was signed on 6 May 2025, work began on 28 August 2025, and the project was paused at 35% after Global South Utilities left in January 2026. pv magazine reported the agreement on 8 September 2026 as if new and named minister Adnan Al-Kaf as signer, but its details match the ministry’s May 2025 post, which names minister Manea bin Yameen. We read it as a rewrite, not a restart, and found nothing showing work resumed.

120 MW / 240 halted January 2026
5 sources
Mokha solar plant, phase 2

UAE-funded, in the Global South Utilities portfolio; paused after the company left in January 2026. NewsYemen reported 98% complete on 11 September 2025, while the company reported 85% in January 2026. As of 19 November 2026 we found nothing showing it entered service.

40 MW halted January 2026
2 sources
Khokha solar plant

UAE-funded, in the Global South Utilities portfolio; stopped at 80% after the company left in January 2026. On 15 October 2026 Yemen Eco ran a headline only saying the electricity corporation approved measures including completing the Khokha and Hays plants; this shows intent, not a restart. Earlier, on 5 October 2026, the same site ran a headline only in which the Public Electricity Corporation denied seizing the solar systems in Hays and Khokha and said technical arrangements to run the subsidised power supply were continuing. As of 19 November 2026 we found nothing showing the plant entered service.

10 MW halted January 2026
5 sources
Hays solar plant

UAE-funded, in the Global South Utilities portfolio; equipment arrived on 16 April 2025, and it stopped at 75% after the company left in January 2026. The Yemen Eco headline of 15 October 2026 on approving completion covers it, but does not show work resumed. Earlier, on 5 October 2026, the same site ran a headline only in which the Public Electricity Corporation denied seizing the solar systems in Hays and Khokha and said technical arrangements to run the subsidised power supply were continuing. As of 19 November 2026 we found nothing showing the plant entered service.

10 MW halted January 2026
4 sources
Socotra solar plant

The only source is MEED’s report on Global South Utilities’ exit, which says the project stopped at 35%. We found no Arabic or official source.

10 MW halted January 2026 MEED: UAE firm withdraws Yemen solar operations (26 Jan 2026)
Lahj solar plant, Bir Nasser, Tuban

On 23 December 2025 a foundation stone was laid for a 20 MW UAE-backed plant at Bir Nasser. On 21 June 2026 the governor discussed a 30 MW government-funded first phase at the same site, with a possible second phase of another 30 MW. Contracting was still being prepared, so no contract or construction is sourced. A ministry post dated 23 December 2025, headline only, names a 20 MW plant at Al-Hawta; we think it is the same Bir Nasser foundation-stone event.

30 MW / 60 announced 21 June 2026
3 sources
Al-Dhale solar plant

Foundation stone laid with UAE backing through Global South Utilities, which left Yemen a month later. We found no later source. It may overlap with the 5 MW Dhale lot in YE08-P14.

20 MW announced 23 December 2025 وزارة الكهرباء والطاقة: وزير الكهرباء يضع حجر أساس المرحلة الأولى لمشروع الطاقة الشمسية في لحج والضالع (23 كانون الأول/ديسمبر 2025)
Abyan solar plant

Foundation stone laid on 24 December 2025 with UAE funding. On 2 April 2026 the minister was still urging that work begin. It may overlap with the 10 MW Abyan lot in YE08-P14, though funder and size differ.

30 MW announced 24 December 2025
2 sources
Private solar plants with IFC support, phase 1

Developer: Al-Saadi company, with IFC support; UNDP funded drafting of the power purchase agreements. What was signed on 28 February 2025 was minutes on the draft contract, not a final contract, so the status stays “announced”. Capacity: Abyan 10 MW, Mahra 10 MW, Al-Dhale 5 MW.

25 MW announced 28 February 2025 وزارة الكهرباء والطاقة: توقيع محضر الاجتماع لمسودة التعاقد مع القطاع الخاص لمشاريع انشاء محطات توليد بالطاقه الشمسية بالشراكة مع مؤسسة التمويل الدولية (28 شباط/فبراير 2025)
Al-Qatn plateau solar plant

A plant with battery storage under build-operate-transfer, in the Wadi and Desert districts. Henan Longxiang (China) with Maico Yemen presented the investment proposal on 9 March 2026. The local authority signed the preliminary partnership agreement on 7 June 2026; the Saba text does not name the other party.

50 MW agreement or memorandum 7 June 2026
3 sources
Hadramawt coast solar plant

The governorate leadership discussed a technical study and field survey with Henan Longxiang (China). No agreement is sourced yet.

200 MW announced 21 May 2026 سبأ: عضو مجلس القيادة الخنبشي يبحث مع شركة صينية دعم مشاريع الطاقة البديلة بحضرموت (21 أيار/مايو 2026)
Qaawa wind power project

The prime minister visited the site in Al-Buraiqa district; UAE funding was planned. We found no later source on the project.

100 MW announced 20 October 2024 وزارة الكهرباء والطاقة: رئيس الوزراء يطلع على موقع مشروع توليد طاقة الرياح بقدرة 100 ميجا وات في منطقة قعوة الساحلية (20 تشرين الأول/أكتوبر 2024)
Lab’ous Yafa water project hybrid solar plant

A small water-pumping plant funded by the World Bank through UNOPS; foundation stone laid on 16 May 2026. The NDC counts captive and off-grid generation, so it stays in the ledger.

2.18 MW announced 16 May 2026 سبأ: وزير المياه ومحافظ لحج يضعان حجر الأساس لحزمة مشاريع مائية وطاقة شمسية في يافع (16 أيار/مايو 2026)
Bir Ahmed water field solar plant

A small plant for water wells, backed by KfW and IOM. A delegation visited the site to see work progress, which is a weak basis for “under construction”. The NDC counts captive generation, so it stays in the ledger.

1.2 MW under construction 19 May 2026 سبأ: وفد ألماني يتفقد موقع مشروع انشاء محطة طاقة شمسية في حقل بئر أحمد (19 أيار/مايو 2026)
Starting point Completed before the contribution period began on 1 January 2026 (the starting point, not counted as progress) · 5 projects
ProjectCapacityStatusStatus dateSatellite imagerySources
Aden solar plant, phase 1

Full operation of all 120 MW was inaugurated on 15 July 2024 (UAE funding, developed by Masdar), so it is the starting point, not progress. On 22 January 2026 Global South Utilities told the Public Electricity Corporation it was evacuating its teams; the company says it handed the Aden and Shabwa plants over running at full technical capacity. The Aden electricity media centre said the same day that the operator had shut both plants down suddenly, and the Ministry of Electricity and Energy said the shutdown came without clear technical justification. In February 2026 one block was out of service after a main transformer fault, and in April 2026 an 8 MW block was still waiting for transformer no. 7 to be repaired, so not all capacity was available in early 2026; in January 2026 Attaqa put its output at about 80% of design capacity.

120 MW operating 15 July 2024 not yet checked on imagery
5 sources
Shabwa solar plant, Ataq

The plant has 15 MW of battery storage and was UAE-funded. Saba dates the inauguration 28 August 2025; the ministry post of the same day says “today, Wednesday”, i.e. 27 August. On 22 January 2026 Global South Utilities told the Public Electricity Corporation it was evacuating its teams; the company says it handed the Aden and Shabwa plants over running at full technical capacity. The Aden electricity media centre said the same day that the operator had shut both plants down suddenly, and the Ministry of Electricity and Energy said the shutdown came without clear technical justification.

53 MW operating 28 August 2025 not yet checked on imagery
3 sources
Mokha solar plant, phase 1

Sources differ on capacity: 15 MW (Attaqa), 20 MW (NewsYemen) and 25 MW (the Presidential Leadership Council chairman’s speech as carried by Saba, May 2024), so the amount is left empty until resolved. UAE-funded; we found no official commissioning date beyond the year.

— operating 2023 not yet checked on imagery
3 sources
Al-Hussein solar plant, Hodeidah National Renewable Energy Project

The plant is in areas run by the authorities in Sanaa and was funded by the Hodeidah support and development fund. Phases 1 and 2 (20 MW) have run since September 2023 and phases 3 and 4 (20 MW) since 11 June 2024. Both sources are non-official, and saba.ye could not be reached.

40 MW operating 11 June 2024 not yet checked on imagery
3 sources
Arab Yemeni Cement Company solar plant

A captive plant for a private cement works in Al-Uyun, Ghayl Ba Wazir, with 5.7 MWh of storage. The NDC counts captive generation, so it stays in the ledger.

13.75 MW operating 27 November 2025 not yet checked on imagery سبأ: العمقي يدشن محطة الطاقة الشمسية العملاقة للشركة العربية اليمنية للأسمنت بقدرة 13.75 ميجاواط (27 تشرين الثاني/نوفمبر 2025)

How we monitor this pledge

Next review · 1 January 2027
Indicator
Share of electricity generated from solar, wind and other renewable sources in total national electricity generation.
Unit
Per cent of total generation, calculated from electricity generated (GWh), not installed capacity.
Share of
Total national electricity generation, covering public grid, off-grid and captive generation recorded in the national energy balance.
Baseline
The NDC names 2022 as the reference year, with the value taken from the national energy balance, but gives no value. We therefore start from what was running when counting began on 1 January 2026, the plants the project ledger lists as the starting point, and count what is completed after that. The required-pace line is not drawn until a generation-share value for the reference year or the start of counting is published.
What counts as a completed output
A renewable plant or system that entered service and generates electricity since 1 January 2026, with a saved source giving its capacity. Announcements, agreements, tenders, projects under construction and solar-panel imports do not count.

Where we follow it

  • Project ledgerMain route

    The pledge’s project ledger: plants and systems that entered service since 1 January 2026, each with a saved source giving its capacity.

  • Published data2 sources
    • IRENA statistics (IRENASTAT) on Yemen’s electricity capacity and generation, the published data closest to the indicator, which under-count off-grid solar.
    • Ember yearly electricity generation data, to compare with IRENA’s figures.
  • Satellite imagery

    Sentinel-2 imagery to check that operating plants stand at their sourced locations, before and after construction.

  • Government announcements

    Government announcements on plants and their completion dates, shown and not counted until checked.

  • Field follow-up

    Field follow-up by local journalists working with Pax Memoria or by its own researchers, to check that plants are running, after a safety judgement.

Proxy

The project ledger records capacity in megawatts, which stands in for the generation share the pledge measures until generation data are published.

We measure something close to the indicator, not the indicator itself, so confidence is “Possible” at most.

Next review 1 January 2027

Sources we watch, and why10 sources
  • وكالة الأنباء اليمنية (سبأ) · official · automatic
    The version of the agency that covers the government that submitted the NDC; it publishes Ministry of Electricity and Energy statements on renewable plants, their agreements and commissioning.
  • وكالة الأنباء اليمنية (سبأ)، نسخة صنعاء · local · manual
    The version of the agency that covers the authorities in Sanaa. We follow it as a non-official source on projects in the areas those authorities run, and do not count what it publishes as an official announcement on the pledge. The site did not respond in the 16 November 2026 test, so it is read by hand.
  • pv magazine · secondary · automatic
    A solar trade outlet that reports tenders, plant contracts and commissioning in the region. Its feed can be read automatically.
  • منصة الطاقة · secondary · automatic
    An Arabic energy news platform; we follow what it publishes on power plants and solar projects in Yemen. Its home page can be read automatically.
  • البنك الدولي: صفحة اليمن · secondary · automatic
    The NDC cites the World Bank’s Yemen Emergency Electricity Access Project (YEEAP) as a benchmark for solar systems; the Bank’s page carries its projects and statements on electricity in Yemen.
  • صندوق المناخ الأخضر: صفحة اليمن · secondary · automatic
    The fund lists approved funding proposals for Yemen and their documents, which name projects, sites and capacities once approved.
  • بيانات الشركات المطوّرة والجهات الممولة للمحطات · secondary · manual
    Developers and funders announce contracts, commissioning and plant capacities, sometimes with details the news leaves out. No company is named until a documented project is found.
  • الوكالة الدولية للطاقة المتجددة (IRENASTAT) · data · automatic
    Yearly renewable capacity and generation statistics for Yemen, the open data closest to the pledge’s measure, although they miss most off-grid solar.
  • Ember: بيانات التوليد السنوية · data · manual
    Yearly generation shares by source. It leaves out off-grid generation, so it is not compared directly with the pledge’s share.
  • صور Sentinel-2 (كوبرنيكوس) · verification · manual
    We use it to check that announced plants exist and run on the ground, and their footprint.

What’s new?

Government announcements we follow. What official bodies announce, as published. Not counted in the total until we check it.

Announcement: UnresolvedTrinasolar and Al-Raebi for Trading and Solar Energy Systems · 20 July 2026 · We return to it: December 2029The two companies will explore a potential 1.5 GW solar project pipeline in Yemen between 2026 and 2029.
Our side
not yet checkedA non-binding memorandum, released from the UAE, naming no site. Al-Raebi is a Yemeni solar systems supplier and Trinasolar a module maker. As of 19 November 2026 we found no specific project resulting from the memorandum; the follow-up date is December 2029.
Announcement: UnresolvedGovernor of Lahj with the Public Electricity Corporation leadership, as reported by Saba · 21 June 2026A 30 MW government-funded first phase of the Lahj solar plant will be built, with a possible second phase of another 30 MW.
Our side
not yet checkedAs of 19 November 2026 we found no contract or start of construction at the Bir Nasser site in Tuban. The announcement gives no date, so it stays unresolved.
Announcement: UnresolvedMinister of Electricity and Energy Adnan Al-Kaf with the economic team, as reported by Saba · 20 April 2026The recovery plan includes taking the Aden plant to 240 MW, a first 40 MW hybrid plant (mazut and solar), and solar plants in Shabwa (53 MW), Hadramawt (100 MW) and Abyan, Lahj, Al-Dhale and Mahra (97 MW) under BOOT.
Our side
not yet checkedThe plan gives no dates. We cannot tell whether the 100 MW Hadramawt plant relates to the Al-Qatn plateau or Hadramawt coast projects. As of 19 November 2026 we found no new plant from the plan in service: the Aden expansion is paused at 35%, the Lahj meeting discussed moving from preparation to implementation, the two Hadramawt projects in the ledger have gone no further than a preliminary investment partnership agreement and talks on preparing a technical study, the Abyan and Al-Dhale plants have gone no further than a foundation stone, and we found no source on the 40 MW hybrid plant. The 53 MW Shabwa plant was running before the plan. The announcement therefore stays unresolved.
All announcements (10)
Announcement: UnresolvedGlobal South Utilities, as reported by MEED · 26 January 2026The company’s $1bn Yemen portfolio covers 13 projects in six governorates with over 1,000 MW in total.
Our side
not yet checkedA US$1bn energy package was announced by the UAE ambassador and the prime minister at the first national energy conference in Aden on 26 November 2025; the ministry’s post on the conference names neither the company nor the number of projects. The company left Yemen in January 2026, and its projects under construction were paused. As of 19 November 2026 we found nothing showing the company withdrew this description or that its paused projects resumed, so the announcement stays unresolved.
Announcement: Not keptMinistry of Electricity and Energy · 28 August 2025 · Announced date: December 2026The Aden solar plant reaches 240 MW in total when phase 2 is completed in 2026.
Our side
contradicted by evidence · Checked on: 17 November 2026MEED reported on 26 January 2026 that phase 2 was paused at 35% after the operator left Yemen, and the recovery plan of 20 April 2026 still listed it as work to be carried out. Evidence from before the announced date counts when it shows the work stopped (team decision of 17 November 2026).
8/202512/2026
Announcement: Not keptAli Al-Shamri, CEO of Global South Utilities, as reported by the Ministry of Electricity and Energy · 28 August 2025 · announced date has passed: June 2026Phase 2 of the Aden solar plant is completed before summer 2026.
Our side
contradicted by evidence · Checked on: 17 November 2026The statement says “next summer”; we set the due date at June 2026. MEED reported on 26 January 2026 that phase 2 had been paused at 35% complete after Global South Utilities left Yemen. The recovery plan reported by Saba on 20 April 2026, weeks before summer, still listed phase 2 as work to be carried out, not as completed.
8/20256/2026
Announcement: Not keptMinister of Electricity and Energy Manea bin Yameen · 6 May 2025Phase 2 of the Aden solar plant takes about 8 months, bringing the plant to 240 MW.
Our side
contradicted by evidence · Checked on: 17 November 2026The statement gives no date, but 8 months from May 2025 means about January 2026. MEED reported on 26 January 2026, about 8 months after the statement, that phase 2 had been paused at 35% complete after Global South Utilities left Yemen. The recovery plan reported by Saba on 20 April 2026 still listed carrying out phase 2 to take the plant to 240 MW.
Announcement: UnresolvedMinistry of Electricity and Energy · 28 February 2025Further solar plants of 73 MW will be built from the remaining financing, after a 25 MW first phase in Abyan, Mahra and Al-Dhale.
Announcement: Kept lateChairman of the Presidential Leadership Council, in a speech reported by Saba · 21 May 2024 · Announced date: June 2024The 120 MW renewable plant in Aden completes its entry into generation next month.
Our side
confirmed · Checked on: 17 November 2026Full operation of the 120 MW Aden plant was inaugurated on 15 July 2024, about two weeks after the end of the announced month, according to Saba.
5/20246/2024

Kept late: 15 July 2024

Announcement: UnresolvedChairman of the Presidential Leadership Council, in a speech reported by Saba · 21 May 2024A 56 MW renewable plant in Shabwa, as a first phase, and 50 MW in Khokha and Hays are under construction, with plants in Hadramawt (25 MW) and Taiz (30 MW) and a 100 MW wind farm at Ras al-Ara being prepared.
Our side
not yet checkedShabwa was built at 53 MW, and Khokha and Hays later appear at 10 MW each. The text does not say the Hadramawt and Taiz plants are solar, and we found nothing later on Ras al-Ara. On 15 October 2026 the Public Electricity Corporation approved measures including completing the Khokha and Hays plants, according to a Yemen Eco headline, so the two plants were not yet complete. The speech gives no dates, so it stays unresolved.